reading material for verifying subcontractors schedules

R
R. Catalan 👤 Member for 20 years 9 months

Dear Martyn,



1) A good start for reading is your project’s contract documents:

- COC (Contractual Milestones dates)

- Specs (Days for approval of submittals)

- Drawings (Physical structure of the project, WBS,)

- BOQ (qtys for verification of durations, required resources, CSI coding and cost loading)



2) Reference books on standard production rates



3) Ron Winter’s website has a lot of good info on baseline verifications).



4) AACEI docs



5) PEO docs



6) Search PP for relevant topics that you might need



On checking delays, you can do the following:

- Delay Analysis - compare Baseline vs. Current

- Periodic Slippage Analysis - compare Current vs. Previous Update



Hope the above helps.



Best regards,

R. Catalan

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear M,



There are a lot of good references in the aacei guides. You will have plenty to ready.



Have a great day.



With kind regards,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts