could be down to the time also, when does the working day start, etc.
expand the start and finish columns so that you see the start date and time and the finish date and time (you might need to format how the date is viewed).
silly question, but if youre calendar is 24 hours and you start something at 8am on the 12th, the finish will be 7.59am on the 13th. If your calendar is working hours/days, your duration should (theoretically) be 8 hours, so, start and finish on same date, duration = 1 day.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks Guys,
I have sorted it out
The working times were 8 till 5 but the calender was 7 till 5
The extra hour was pushing the tasks over to the next day
Thanks david & nicolas
Hi Andrew
Check that
1) duration of day
in Tools Options Calendar
is compatible with
2) dayly working time
in Tools Modify working time.
If you tell MSP
that
1) your "day" is 10 hours long
but
2) you allow only 8-12am and 2-6pm you will need
finish the next day.
hth
Trying to "fill down"to make my start times all 7 am but wont let me make the changes.
aaaahhhrrrr
Great idea
I have found the problem in the start times are all over the place, but my calender starts at 7 and finishes at 5 every day
The same calender is assigned to all tasks.
Ill keep digging
could be down to the time also, when does the working day start, etc.
expand the start and finish columns so that you see the start date and time and the finish date and time (you might need to format how the date is viewed).
D.
Working days are set to 8hr days
I figure it has something to do with the calender day anfd hrs but cant put me finger on it!
how long are your days?
silly question, but if youre calendar is 24 hours and you start something at 8am on the 12th, the finish will be 7.59am on the 13th. If your calendar is working hours/days, your duration should (theoretically) be 8 hours, so, start and finish on same date, duration = 1 day.
try putting your duration down as 8 hours.
D.