Auto cost rule in P6

S
shahajahan azeez 👤 Member for 15 years 7 months

Dear All,

After Updating the Program in P6,we have number of -ve floats, how to check the certain value of -ve Float    (For example  -33d Float) ???  

Regards

Shahajahan

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Le,



Go to Enterprise --> Projects --> Highlight your current open project --> Project Details, Calculations Tab, Resource Assignments..



Hope this helps.



Regards,



Arnold

L
Le Tuan 👤 Member for 18 years 4 months

Dear Arnold.

Would you please to show me where untick of No.2 ? I cannot find it.

Thanks

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Anbin,



There are two options you can apply.



1. Use Physical % complete.

2. Untick "Recalculate Actual Units and Cost when duration % complete changes".



Regards,



Arnold

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts