Dear All,
After Updating the Program in P6,we have number of -ve floats, how to check the certain value of -ve Float (For example -33d Float) ???
Regards
Shahajahan
Hi Le,
Go to Enterprise --> Projects --> Highlight your current open project --> Project Details, Calculations Tab, Resource Assignments..
Hope this helps.
Regards,
Arnold
Dear Arnold.
Would you please to show me where untick of No.2 ? I cannot find it.
Thanks
Thanks a lot.,
Regards,
Anbin Ponnith
Hi Anbin,
There are two options you can apply.
1. Use Physical % complete.
2. Untick "Recalculate Actual Units and Cost when duration % complete changes".
Regards,
Arnold