Baseline Updating & LOE Issue
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Ruel,
Thanks for the reply but you can not change BL Start and Finish dates manually by adding their columns and changing! The only way you can change baseline is either updating that or rebaseline?! As I mentioned, rebaseline does have issues which P6.2 did not fix yet and I want to know if others have solutions. Please read my original question.
Rgds, Sean
Sean,
Is your schedule date driven? What we do here is we add 2 columns which are BL Start and BL Finish (as targets) and change the start and finish columns to actual start/finish respectively. Input the actual work dates on a particular scope then make a run (F9; datadate).
Hope this helps!
Cheers!
Ruel