Baseline Updating & LOE Issue

S
Sean Moghimi 👤 Member for 19 years 7 months

Hi Ruel,



Thanks for the reply but you can not change BL Start and Finish dates manually by adding their columns and changing! The only way you can change baseline is either updating that or rebaseline?! As I mentioned, rebaseline does have issues which P6.2 did not fix yet and I want to know if others have solutions. Please read my original question.



Rgds, Sean

R
Ruel Camaquin 👤 Member for 17 years 7 months

Sean,



Is your schedule date driven? What we do here is we add 2 columns which are BL Start and BL Finish (as targets) and change the start and finish columns to actual start/finish respectively. Input the actual work dates on a particular scope then make a run (F9; datadate).



Hope this helps!



Cheers!



Ruel

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts