i am making S cruves for Early and Late loading values extracted from P3.1 and P6 to Excel. If u know the method to generate curve within the P6 with 2 baselines, i would like to know too.
can you please send me the copy of your S curve prepared on WBS earned value report based on activity % weighting (Project->WBS) two curves (early vs. late dates)
A late earned value of progressing program.... Is it useful to use when some of the activies had a negative total float?
As far as project that I involved with we usually use an early and late curve in planning stage wherein the lowest total float is zero. Wish to enhance my knowledge if you could share me how you extract a late data with activities having a negative total float.
This is possible. Make two copies of your baseline schedule. Then assign it into your current schedule. If you need the steps, forward to me your email.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
i am making S cruves for Early and Late loading values extracted from P3.1 and P6 to Excel. If u know the method to generate curve within the P6 with 2 baselines, i would like to know too.
Please send me your steps to [email protected]
Thanks in advance
Regards
Haris
Joe,
can you please send me the copy of your S curve prepared on WBS earned value report based on activity % weighting (Project->WBS) two curves (early vs. late dates)
Thanks & regards
V
[email protected]
Dear all,
A late earned value of progressing program.... Is it useful to use when some of the activies had a negative total float?
As far as project that I involved with we usually use an early and late curve in planning stage wherein the lowest total float is zero. Wish to enhance my knowledge if you could share me how you extract a late data with activities having a negative total float.
Regards,
RL
Hi Arnold,
I already received your email with attachment.
Many thanks,
Joe
Dear Arnold,
Pls send me too..
[email protected]
Thanks,
Shah
Dear Arnold,
This is to acknowledge I receive the file.
More power to you.
Many thanks,
Scarlett
Hi Jose,
Already sent.
Hi Arnold,
Please send me to my email address:
[email protected]
Thanks in advance,
Joe
Dear Arnold,
Please send me:
[email protected]
Many thanks
Scarllet
Hi Jose,
This is possible. Make two copies of your baseline schedule. Then assign it into your current schedule. If you need the steps, forward to me your email.
Regards,
Arnold