Calculated user-defined fields

R
Rajesh Khanna Sake 👤 Member for 19 years 10 months

I was actually trying to calculate "Calendar Days" - I could assign a formula to the user-defined field and it is working fine at the activity level. But, at the WBS summary level - it is adding up "calendar days" associated with all the activities in that level which I believe is incorrect.

Is there any way we can change the way the summaries are rolled up just for the user defined fields?



Many Thanks,

Rajesh

R
Ronald Winter 👤 Member for 23 years 6 months

The web-based P6 has calculated fields but this feature is not in the Client/Server version.