Peak Manpower in the Resource Histogram
Forum Sponsor
Top Posters
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Can you please send a copy at [email protected]
Thanks in advance
Hi Eric,
Could you please also send me a copy?
[email protected]
thanks very much.....
Walshy
Hello Eric,
Please send me a copy also at [email protected].
Thanks,
Amjad
Can you [lease send a copy at [email protected]
thanks!
jojie
Hello Eric,
Can you please also send a copy at [email protected]
Thank you in advance
Artur
Can you please send a copy at [email protected].
Thanks in advance
Eric,
Pls send me a copy to [email protected]
Thanks,
R. Catalan
Hello Eric,
Here is my email adress [email protected]
Thanks for your time.
Glenn
Hello Glenn,
I dont know If P6 do this, I guess that you can generate a report with those parameter in the "Reports" features but I am not familiar with it.
Give me your mail adress I will forward you a document relating how I manage to export data in excel to generate Curves and Histograms
Regards
Dear Eric,
I tried this option and it is shows the over allocated budgedted units in histogram form but is it possible in P6 to generate a report in tabular form showing the average, peak & total budgeted quantity like in P3. i need this values because I am presenting the manpower histogram in excel. your response would be very much appreciated.
Thanks,
Glenn
Hello,
Go to the "resource usage profile", right click on the histogram and select "Resource Usage Profile Options".
In Additional Data Options, select "Show Limits" and "Show Overallocation", it should works
Regards
Eric
P3 offered "Total, Peak, Average"
P6 just has "total or average"