Peak Manpower in the Resource Histogram

E
Eric EVRARD 👤 Member for 19 years 6 months

Hello Glenn,

I don’t know If P6 do this, I guess that you can generate a report with those parameter in the "Reports" features but I am not familiar with it.

Give me your mail adress I will forward you a document relating how I manage to export data in excel to generate Curves and Histograms

Regards

G
Glenn Dexter Ubaldo 👤 Member for 17 years

Dear Eric,



I tried this option and it is shows the over allocated budgedted units in histogram form but is it possible in P6 to generate a report in tabular form showing the average, peak & total budgeted quantity like in P3. i need this values because I am presenting the manpower histogram in excel. your response would be very much appreciated.



Thanks,

Glenn

E
Eric EVRARD 👤 Member for 19 years 6 months

Hello,

Go to the "resource usage profile", right click on the histogram and select "Resource Usage Profile Options".

In Additional Data Options, select "Show Limits" and "Show Overallocation", it should works

Regards

Eric

D
David Kelly 👤 Member for 21 years 8 months

P3 offered "Total, Peak, Average"



P6 just has "total or average"

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts