P3.1 to P6.3 - Errors with calanders and dates

T
Teague K 👤 Member for 17 years 7 months
D
Dieter Wambach 👤 Member for 19 years 5 months

Teague



P6 internally only keeps hours. Just to display in the user interface it can be calculated into different units - based on your user preferences and the admin preferences for time units. Especially beginners for Primavera have many difficulties with this issue.

Primavera announced some modification in version 7



Regards

Dieter

T
Teague K 👤 Member for 17 years 7 months

Thanks for your response Dieter,



I believe there is very little change in P6.2 to P6.3.



I will take a look at it and try to import it again.



I would like to keep the schedule in days in P6 though.

D
Dieter Wambach 👤 Member for 19 years 5 months

Teague



I have no experience with P6.3 - we have P6.2.1 - but the import should be equivalent.



When you run through the wizzard, you’ll find a button "Advanced". Select this one to select between hours and days as a unit.



Global change: Original duration will not satisfy, e.g. remaining -, actual duration.



Regards

Dieter


Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts