P6 - resource early start vs activity early start
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Phil
Resource Early Start may be different for each assignment. From Activity point of view its a list. Which one to be used?
I dont know how group&sort and filtering isnt robust for the assignment view.
That you are running a true ’resource dependent’ might be one more reason to have a closer look at this view.
Regards
Dieter
I publish Activity layouts in HTM format because the grouping, sorting, and filterig is more user friendly across multiple projects. I do not want to publish from assignments layouts becasue Grouping, sorting, and filtering is not as robust. I want to publish a layout that contains data elements from both activity and assignment view. Specifically, i want to include resource "remaining early start" in an activity layout, that i will publish as an HTM file. I suspect no one is running a true resource dependent schedule?
Phil
Therefore you have the view "Assignments" - "Start" vs "Activity Start".
Regards
Dieter