P6 - resource early start vs activity early start

D
Dieter Wambach 👤 Member for 19 years 5 months

Phil



Resource Early Start may be different for each assignment. From Activity point of view it’s a list. Which one to be used?



I don’t know how group&sort and filtering isn’t robust for the assignment view.



That you are running a true ’resource dependent’ might be one more reason to have a closer look at this view.



Regards

Dieter

P
Phil Montgomery 👤 Member for 19 years 3 months

I publish Activity layouts in HTM format because the grouping, sorting, and filterig is more user friendly across multiple projects. I do not want to publish from assignments layouts becasue Grouping, sorting, and filtering is not as robust. I want to publish a layout that contains data elements from both activity and assignment view. Specifically, i want to include resource "remaining early start" in an activity layout, that i will publish as an HTM file. I suspect no one is running a true ’resource dependent’ schedule?

D
Dieter Wambach 👤 Member for 19 years 5 months

Phil



Therefore you have the view "Assignments" - "Start" vs "Activity Start".



Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts