Performance % complete

I
Izam Zakaria 👤 Member for 20 years 1 month

Arnold,



Performance % complete is KPI right?

As my understanding you just need Earned Hours to divide actual cumulative manhours. From there u will see how good your current project status.

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Musawar,



Performance % Complete is related to Cost. If you don’t have cost loaded to your programme then you don’t get P%C.



If you have assign cost then you need to check your cost not equal to zero.



HTH.



Arnold