Hi Izam,
Performance % Complete is used to compute earned value and may be based on the activity % complete.
KPI is the Key Performance Indicator. Try to check this link:
http://en.wikipedia.org/wiki/Key_performance_indicators
HTH.
Regards,
Arnold
Arnold,
Performance % complete is KPI right?
As my understanding you just need Earned Hours to divide actual cumulative manhours. From there u will see how good your current project status.
Hi Musawar,
Performance % Complete is related to Cost. If you dont have cost loaded to your programme then you dont get P%C.
If you have assign cost then you need to check your cost not equal to zero.
HTH.
Arnold