a) Open the projects you want to insert, then click Window, New window, select the projects and click OK; in this case, the projects inserted in the new window are linked to the source files
b) Click Insert, Project, and select one by one the projects you need; in this case, it is possible to link (default) or not (clear the check box)
If you use this second method and do not link the target to the source, it is 10% normal that the inserted projects (I should say "tasks") will not be deleted if you delete the source (I should say "original") projects, and vice versa.
They could be tasks that you put into the Master project.
You didnt say which view you are using. If its Resource Usage then they could be tasks that were part of a project schedule you inserted while using a resource pool and then lost/mangled the links to that file.
You havent really given us a lot to work from. You didnt mention the version or service pack number you have, you havent told us which view you are using, you say "delete" and "move" but its not clear if you mean within the project or within the folder and "doesnt work at all" is -- you must admit -- not exactly a very precise description of your situation.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Kirpal,
To insert projects can be made in two ways:
a) Open the projects you want to insert, then click Window, New window, select the projects and click OK; in this case, the projects inserted in the new window are linked to the source files
b) Click Insert, Project, and select one by one the projects you need; in this case, it is possible to link (default) or not (clear the check box)
If you use this second method and do not link the target to the source, it is 10% normal that the inserted projects (I should say "tasks") will not be deleted if you delete the source (I should say "original") projects, and vice versa.
Hope this helps
Alexandre
They could be tasks that you put into the Master project.
You didnt say which view you are using. If its Resource Usage then they could be tasks that were part of a project schedule you inserted while using a resource pool and then lost/mangled the links to that file.
You havent really given us a lot to work from. You didnt mention the version or service pack number you have, you havent told us which view you are using, you say "delete" and "move" but its not clear if you mean within the project or within the folder and "doesnt work at all" is -- you must admit -- not exactly a very precise description of your situation.
Hi Kirpal,
What service pack are you using?
I had a similar problem with MS Project 2k3, I downloaded SP3 and haven’t had any problems since.
Regards,
Darren