I go for what Arnold said...
Hi Michael,
Try to use Physical % Complete. It is mnually users input.
Regards.
hi arnold,
when i am changing duration % complete, remaining duration still changes.
i already untick the option you posted below.
my question is to unlink the duration % complete and RD.
thanx again
Hi Michael,
Go to Project Detail --> Calculations Tab --> Under Resource Assignments, untick the "Recalculate Actual Units and Cost when duration % complete changes".
Regards,
Arnold