Arnold Puy 👤 Member for 19 years 1 month

Hi Michael,



Try to use Physical % Complete. It is mnually user’s input.



Regards.

M
michael ramos 👤 Member for 17 years 4 months

hi arnold,



when i am changing duration % complete, remaining duration still changes.



i already untick the option you posted below.



my question is to unlink the duration % complete and RD.



thanx again


A
Arnold Puy 👤 Member for 19 years 1 month

Hi Michael,



Go to Project Detail --> Calculations Tab --> Under Resource Assignments, untick the "Recalculate Actual Units and Cost when duration % complete changes".



Regards,



Arnold