UPDATED FINISH MILESTONE?

M
marwan ibrahim 👤 Member for 18 years

Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."



Cheers!

A
Arnold Puy 👤 Member for 19 years 1 month



Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Marwan,



If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.



Regards,



Arnold


M
marwan ibrahim 👤 Member for 18 years

Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts