Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."
Cheers!
Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.
I respect ur views Arnold. Maybe we have to wait for others comments.
I dont think so.
Hi Marwan,
If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.
Regards,
Arnold
Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.