UPDATED FINISH MILESTONE?

M
marwan ibrahim 👤 Member for 18 years 1 month

Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."



Cheers!

A
Arnold Puy 👤 Member for 19 years 2 months



Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Marwan,



If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.



Regards,



Arnold


M
marwan ibrahim 👤 Member for 18 years 1 month

Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts