I Urgently need a Sample Programme Details of activities WBS Constraints every possible details of any Airport I got Interview and I have to show them a Samply Project please any one e-mail me asap regards
For airport project, always look for someone who has an experience with ORATT(Operational Readiness, Testing & Transfer). These people know excatly what to look for in an airport project schedule in order to make sure that the airport will open successfully and on schedule. The people I worked with before who does this kind of work has an extensive experience with ICAO, thats why they are very knowlegeable about airport construction and regulations.
No airport project has become successful just because the building is constructed. It will all boil down to the various airport systems and its integration. The heart of this is the Baggage Handling System. Remember chep lap kok?
To make the long story short, make sure that the various airport systems have their realistic interface dates shown in the schedule from design to execution.
Please remember when building your schedule that you remember more than just the civil/construction aspect.
Airports are usually confined to specific codes and rules from various organisations from the local Civil Defence to an International Safety Body.
You will need to consider Special and Specific Airport Systems, large PAX safety systems, boarding and customs gates, alarms and life safety, aircraft interaction, and the list goes on and on.
If you are asking for the schedule, Ill assume that you are working on an airport project, no doubt with a firm that has experience in this field. You should perform Front End Engineering Design Discussions with your M&E Managers, HS&E Teams, Design Management and Project Teams.
If you are involved in a the construction of a specific section of the works, a hangar for example, you still need to consider the aircraft and airport interaction.
When you have built your schedule, resourced & levelled it, make sure the constraints and logic are spot-on, I will be absolutely shocked if you do not get variation or change or are delayed by your client, so be prepared to impact your programme.
This advice is from experience, I spent two years performing the Delay Analysis on a major Airport in the Middle East, and that was with a good planning team already in place for the Contractor.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
As far as I can tell ,no-one ever actually offered to email out a copy of an airport schedule in the first place.
Thread locked.
may i ask you to have a copy of Airport Schedule on my mail [email protected]
I will be thankful for this act of kind help
may i ask you to have a copy of Airport Schedule on my mail [email protected]
I will be thankful for this act of kind help
I will be really happy if you send me a sample of airport construction schedule also. [email protected]
Mr. Sridhar
may i ask you to have a copy of Airport Schedule on my mail [email protected]
I will be thankful for this act of kind help
I Urgently need a Sample Programme Details of activities WBS Constraints every possible details of any Airport I got Interview and I have to show them a Samply Project please any one e-mail me asap regards
Regards
Nadeem Akram
London UK
[email protected]
Dear
Can u please send me this also.
My Mail Id is [email protected]
Thanks
nasim
Please can I also have the info on airports sent to [email protected]
Many thanks
For airport project, always look for someone who has an experience with ORATT(Operational Readiness, Testing & Transfer). These people know excatly what to look for in an airport project schedule in order to make sure that the airport will open successfully and on schedule. The people I worked with before who does this kind of work has an extensive experience with ICAO, thats why they are very knowlegeable about airport construction and regulations.
No airport project has become successful just because the building is constructed. It will all boil down to the various airport systems and its integration. The heart of this is the Baggage Handling System. Remember chep lap kok?
To make the long story short, make sure that the various airport systems have their realistic interface dates shown in the schedule from design to execution.
My 2 cents.
Please remember when building your schedule that you remember more than just the civil/construction aspect.
Airports are usually confined to specific codes and rules from various organisations from the local Civil Defence to an International Safety Body.
You will need to consider Special and Specific Airport Systems, large PAX safety systems, boarding and customs gates, alarms and life safety, aircraft interaction, and the list goes on and on.
If you are asking for the schedule, Ill assume that you are working on an airport project, no doubt with a firm that has experience in this field. You should perform Front End Engineering Design Discussions with your M&E Managers, HS&E Teams, Design Management and Project Teams.
If you are involved in a the construction of a specific section of the works, a hangar for example, you still need to consider the aircraft and airport interaction.
When you have built your schedule, resourced & levelled it, make sure the constraints and logic are spot-on, I will be absolutely shocked if you do not get variation or change or are delayed by your client, so be prepared to impact your programme.
This advice is from experience, I spent two years performing the Delay Analysis on a major Airport in the Middle East, and that was with a good planning team already in place for the Contractor.
Hi Sridhar,
Send me also a copy at [email protected]
Many thanks,
R. Catalan
Mr. Sridhar
may i ask you to have a copy of Airport Schedule on my mail [email protected]
I will be thankful for your help
Osama
Dear V,
The best start would be to have the following General activities and then start expanding the details as per your Contract requirements.
I) Infrastructure
Civil - Cut and Fill, Base course, Asphalt, concreting
Electrical - Power, Lighting, Low Current
Mechanical - Plumbing, District Cooling
II) Buildings
regular activities + special designs.
The special systems and requirements will have to be read from the drawings, specifications and BOQs.
Best,
Samer
Mr. Sridhar
may i ask you to have a copy of Airport Schedule on my mail [email protected]
I will be thankful for this act of kind help
Hi Sridhar,
Can you send me also Please at [email protected]
Arnold
Dear
Can u please send me this also.
My Mail Id is [email protected]
Thanks
Ashutosh Nema
Hi, Sridhar
Could you please send me WBS and Acrivities of whole schedule of typical airport project.
Thanks in advance
[email protected]
Regards
Salah
Dear Sir
may i ask you to have a copy of this schedule on my mail [email protected]
I will be thankful for your kind help
Hai Sridhar,
I need the complete schedule if you have otherwise whatever you have send it to my mail id
[email protected]
asasa
Ponnaganti,
Could you send to me also.
[email protected]
Hi
Hello Venkatarao.B which kind of Airport schedule you are looking for? Is that an international Airport or Domestic Airport?
i Have a little Experince in AirportSchedule Pepration, i was there in Schedule perpration of Doha International Airport,
so what are you looking for? is the Schedule of entire project or related to only some Utlity area??