Percent weight in Primavera P3 S-curve

M
mimoune djouallah 👤 Member for 19 years 9 months

hi



you need to assign a resource, "call it manhour for simplification" to your program,

let’s say the total budget quantity for your program will be 100 Hours. thus :



Engineering = 25 hour

Procurement/Fab = 15 hour

Construction = 55 hour

Commissioning = 5 hour





HTH