Select INT4 and click OPEN when you want to open the whole group of projects
Select AR07 and click OPEN when you want to open this project only
You will have to assign the same WBS and Activity Codes to AR07 and BU09 than in the other projects if you want to display these 2 projects with the whole group.
Thanks a lot, it works! But how will it appear under INT4 when under open dialog box? If however I want to open just AR07 or BU09 without opening INT4?
The open project dialog box looks like above. I want to put AR07 and BU09 wihin INT4 in order that AR07 and BU09 will be within INT4 Project. ALQU, BUIS and DUBL were already within INT4 Project. How can I do that? Thank you very much!
do you 2 projects already exist? then use the Copy command to copy these projects to new projects; at the bottom of the dialog box, enter the name (4 digits) of the project group you want to associate thes 2 projects to
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Select INT4 and click OPEN when you want to open the whole group of projects
Select AR07 and click OPEN when you want to open this project only
You will have to assign the same WBS and Activity Codes to AR07 and BU09 than in the other projects if you want to display these 2 projects with the whole group.
Refer to the APEX projects group as an example.
Cheers,
Alexandre
Thanks a lot, it works! But how will it appear under INT4 when under open dialog box? If however I want to open just AR07 or BU09 without opening INT4?
Click Tools, Project Utilities, Copy
Browse to AR07
In the "Project Group" field, enter INT4
In the "project Name" field, enter AR07
In the "Project ID" field, enter a 2 digit ID (refer to HELP for more explanations)
Same procedure for BU09
You will then delete the source projects if you wish
Alexandre
Name Number/Version Title
AR07 Target R07 - Al Rigga Station
BU09 Target R09 - Burjuman Station
INT4 OG Stations Accelerated Program- Rev05
ALQU Target 17-AlQuoz
BUIS Target 16-Business Bay
DUBL Target 26-Dubal
The open project dialog box looks like above. I want to put AR07 and BU09 wihin INT4 in order that AR07 and BU09 will be within INT4 Project. ALQU, BUIS and DUBL were already within INT4 Project. How can I do that? Thank you very much!
Ernani,
do you 2 projects already exist? then use the Copy command to copy these projects to new projects; at the bottom of the dialog box, enter the name (4 digits) of the project group you want to associate thes 2 projects to