How to Move Date Sight Line?

S
Sam Abbitt 👤 Member for 17 years 4 months
S
Sajid Balma 👤 Member for 19 years

1. Click Data

2. Click Calendars...

3. Click Global Calendar

4. Click Standard...

5. Select a new date under Data Date

Close windows

Now your schedule has new sight line as per your new data date without any change in the schedule.



TAAAADAAAA

S
Sam Abbitt 👤 Member for 17 years 4 months

Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name".



Any ideas?

J
Jean-Philippe Sampieri 👤 Member for 19 years 4 months

Hi Sam,



If it is only for printing, a turnaround for your problem may be:

(Make backups before !)

- Make a copy of your schedule,

- Set the copy as a target for your schedule.

- Update the data date of the current schedule

- In the bar chart, hide all the bars but the Target Bar.



Hope this helps

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts