How to Move Date Sight Line?
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Thanks everyone.
1. Click Data
2. Click Calendars...
3. Click Global Calendar
4. Click Standard...
5. Select a new date under Data Date
Close windows
Now your schedule has new sight line as per your new data date without any change in the schedule.
TAAAADAAAA
Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name".
Any ideas?
Hi Sam,
If it is only for printing, a turnaround for your problem may be:
(Make backups before !)
- Make a copy of your schedule,
- Set the copy as a target for your schedule.
- Update the data date of the current schedule
- In the bar chart, hide all the bars but the Target Bar.
Hope this helps