Planning, Scheduling & Programming Discussion Member for 24 years 5 months Member for 24 years 5 months Submitted by Roberto Jr Bustos on Tue, 2008-12-23 06:17 Permalink RE: P6 Base line variance ow! i didnt see that there are answers already:) anyway, cheers! Member for 24 years 5 months Member for 24 years 5 months Submitted by Roberto Jr Bustos on Tue, 2008-12-23 06:15 Permalink RE: P6 Base line variance if you have established the baseline already, then just go to filter and... under parameters: Variance - BL1 Finish Date (choose from the pulldown items) Is: is less than Value: 0 so any activities with negative variance will be shown in your gantt chart. pls tell me if this is not what you are looking for, maybe i read it wrong:) Member for 18 years 1 month Member for 18 years 1 month Submitted by Bob Foden on Tue, 2008-12-23 06:13 Permalink RE: P6 Base line variance Cheers Shimmo, Dont know how I missed them "variances" in the filter list. Must be too many mince pies !!!!!! Bob Member for 18 years 9 months Member for 18 years 9 months Submitted by James Shimmon on Tue, 2008-12-23 06:08 Permalink RE: P6 Base line variance Bob Set up a filter to pick up any of the following Variance-BL Project Start Date - Greater than 0 days Variance-BL Project Start Date - Less than 0 days Variance-BL Project Finish Date - Greater than 0 days Variance-BL Project Finish Date - Less than 0 days Cheers Shimmo Log in or register to post comments
Member for 24 years 5 months Member for 24 years 5 months Submitted by Roberto Jr Bustos on Tue, 2008-12-23 06:17 Permalink RE: P6 Base line variance ow! i didnt see that there are answers already:) anyway, cheers!
Member for 24 years 5 months Member for 24 years 5 months Submitted by Roberto Jr Bustos on Tue, 2008-12-23 06:15 Permalink RE: P6 Base line variance if you have established the baseline already, then just go to filter and... under parameters: Variance - BL1 Finish Date (choose from the pulldown items) Is: is less than Value: 0 so any activities with negative variance will be shown in your gantt chart. pls tell me if this is not what you are looking for, maybe i read it wrong:)
Member for 18 years 1 month Member for 18 years 1 month Submitted by Bob Foden on Tue, 2008-12-23 06:13 Permalink RE: P6 Base line variance Cheers Shimmo, Dont know how I missed them "variances" in the filter list. Must be too many mince pies !!!!!! Bob
Member for 18 years 9 months Member for 18 years 9 months Submitted by James Shimmon on Tue, 2008-12-23 06:08 Permalink RE: P6 Base line variance Bob Set up a filter to pick up any of the following Variance-BL Project Start Date - Greater than 0 days Variance-BL Project Start Date - Less than 0 days Variance-BL Project Finish Date - Greater than 0 days Variance-BL Project Finish Date - Less than 0 days Cheers Shimmo
Member for
24 years 5 monthsRE: P6 Base line variance
ow! i didnt see that there are answers already:)
anyway, cheers!
Member for
24 years 5 monthsRE: P6 Base line variance
if you have established the baseline already, then just go to filter and...
under parameters: Variance - BL1 Finish Date (choose from the pulldown items)
Is: is less than
Value: 0
so any activities with negative variance will be shown in your gantt chart.
pls tell me if this is not what you are looking for, maybe i read it wrong:)
Member for
18 years 1 monthRE: P6 Base line variance
Cheers Shimmo,
Dont know how I missed them "variances" in the filter list. Must be too many mince pies !!!!!!
Bob
Member for
18 years 9 monthsRE: P6 Base line variance
Bob
Set up a filter to pick up any of the following
Variance-BL Project Start Date - Greater than 0 days
Variance-BL Project Start Date - Less than 0 days
Variance-BL Project Finish Date - Greater than 0 days
Variance-BL Project Finish Date - Less than 0 days
Cheers
Shimmo