P6 Base line variance

B
Bob Foden 👤 Member for 18 years 9 months
R
Roberto Jr Bustos 👤 Member for 25 years 1 month

if you have established the baseline already, then just go to filter and...



under parameters: Variance - BL1 Finish Date (choose from the pulldown items)



Is: is less than

Value: 0



so any activities with negative variance will be shown in your gantt chart.



pls tell me if this is not what you are looking for, maybe i read it wrong:)

B
Bob Foden 👤 Member for 18 years 9 months

Cheers Shimmo,



Don’t know how I missed them "variances" in the filter list. Must be too many mince pies !!!!!!



Bob

J
James Shimmon 👤 Member for 19 years 5 months

Bob

Set up a filter to pick up any of the following



Variance-BL Project Start Date - Greater than 0 days

Variance-BL Project Start Date - Less than 0 days

Variance-BL Project Finish Date - Greater than 0 days

Variance-BL Project Finish Date - Less than 0 days



Cheers



Shimmo

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts