P6 Base line variance

Member for

24 years 5 months

ow! i didnt see that there are answers already:)

anyway, cheers!

Member for

24 years 5 months

if you have established the baseline already, then just go to filter and...



under parameters: Variance - BL1 Finish Date (choose from the pulldown items)



Is: is less than

Value: 0



so any activities with negative variance will be shown in your gantt chart.



pls tell me if this is not what you are looking for, maybe i read it wrong:)

Member for

18 years 1 month

Cheers Shimmo,



Don’t know how I missed them "variances" in the filter list. Must be too many mince pies !!!!!!



Bob

Member for

18 years 9 months

Bob

Set up a filter to pick up any of the following



Variance-BL Project Start Date - Greater than 0 days

Variance-BL Project Start Date - Less than 0 days

Variance-BL Project Finish Date - Greater than 0 days

Variance-BL Project Finish Date - Less than 0 days



Cheers



Shimmo