ow! i didnt see that there are answers already:)
anyway, cheers!
if you have established the baseline already, then just go to filter and...
under parameters: Variance - BL1 Finish Date (choose from the pulldown items)
Is: is less than
Value: 0
so any activities with negative variance will be shown in your gantt chart.
pls tell me if this is not what you are looking for, maybe i read it wrong:)
Cheers Shimmo,
Dont know how I missed them "variances" in the filter list. Must be too many mince pies !!!!!!
Bob
Bob
Set up a filter to pick up any of the following
Variance-BL Project Start Date - Greater than 0 days
Variance-BL Project Start Date - Less than 0 days
Variance-BL Project Finish Date - Greater than 0 days
Variance-BL Project Finish Date - Less than 0 days
Cheers
Shimmo