Planning using Meters - P6 - NATM Tunnel

A
A D 👤 Member for 19 years 1 month

If u r not getting spreadsheet in ur preview, then go to page set up --> Options --> Check on SPREADSHEET box.



KHALLAS!!!



:-)

S
Shane Stanford 👤 Member for 17 years 8 months

Yep, thank you Dieter, Raviraj and Vladimir.



All sorted now... Now all I have to do is print the resource usage chart and the gantt on the same page :-)

D
Dieter Wambach 👤 Member for 19 years 6 months

Shane

I don’t really understand your item.

P6 has the resource type "material".

1. Define required unit of measure - if not yet done:

Admin --> Admin Categories --> Units of Measure --> Add ...

2. Define Resource of type Material - under Details.

3. Assign this resource to those activities you’ll need.

4. To have an overview and the results of your planning: View--> Show on bottom --> either Resource Usage Spread or Resource Usage Histogram. One restriction: you can just show resources with the same unit of measure in the histogram.

Was this your question?

Regards

Dieter

S
Shane Stanford 👤 Member for 17 years 8 months

All I really need it to do is display how many meters we are are expecting to do each week, and be able to put in actuals throughout the project. The resource schedule looks like the ideal layout, but it edits when scheduled.



Thanks for your help so far too.



Shane

V
Vladimir Liberzon 👤 Member for 25 years 5 months

Actually there is a need to link a lot of data with these meters (physical quantities of work - physical volumes) - material requirements per each meter, cost per meter, resource productivities in meters per hour, etc. Unfortunately Primavera do not plan physical quantities of work to be done, if you need it try to find some other software. Workarounds do not help.

A
A D 👤 Member for 19 years 1 month

Shane,



Check ur resource levelling options. (Go to Tools --> Level Resources)



Uncheck theses three options:

- Automatically level resources when scheduling, AND

- Preserve scheduled early and late dates

- Level all resources



Cheers,



Rav

S
Shane Stanford 👤 Member for 17 years 8 months

Thanks Raviraj,



I think I got it now - they seem to be a little erratic though, as I would like to click on week one and assign 42 meters, then week two and assign 36 meters and so on. but when I change datesand reschedule, the usage changes.

A
A D 👤 Member for 19 years 1 month

Add a resource and then add budgeted quantity. U can check Resource usage spreadsheet.


Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts

Our Partners