There are some more items to be observed because many start using MSP without any training or consideration. Having imported many MPP-files I found 80 to 90% with user errors, mainly:

- Calendars misused and not maintained ("P6 calculates wrong dates!" "If you would have included Christmas or other exceptions you would find the same dates.")

- Planned with fixed durations but the default "effort driven" still used inclusive resource calendars.

Many more are quite common. So first I open a project in MSP to check before import.

Regards

Dieter

D
Dieter Wambach 👤 Member for 19 years 5 months

Graeme

MSP must be installed on the pc from where you start the import. Primavera uses OLE-technique (Object Linking and Embedding) which means it uses MSP functions for import and export of MPP-files. It’s independent from server or standalone.



Good luck!

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts