One more mistake maybe that you assigned the Target correctly but while selecting the target bar from format>bar in bar description you selected the wrong start/finish . Format>bar ,You have to select target bar or make a new target Bar and assign - Target 1 Early start for start and Target 1 Early finish for finish
If you have already created a target and assigned the same, then the bars moving along with the current bars can be of 2 reasons.
1. you might have created the schedule target, but forgot to assign it as the primary basleine. in which case, the target bars you see at the bottom are just the current schedule bars showing up as target bars.
2. you might have forgotten to check cell to display the primary baseline bars. You can do that by clicking on the bar options, and check the box against the primary baseline to be displayed.
Unless you UPDATE TARGET , Tools>Project Uilities> Target and then update , selecting the required updates , it should not update the target and the taret bars should not move.
If you want you can send me the schedule to [email protected] and i will check it for you.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello James,
One more mistake maybe that you assigned the Target correctly but while selecting the target bar from format>bar in bar description you selected the wrong start/finish . Format>bar ,You have to select target bar or make a new target Bar and assign - Target 1 Early start for start and Target 1 Early finish for finish
regards
deb
Hi James,
If you have already created a target and assigned the same, then the bars moving along with the current bars can be of 2 reasons.
1. you might have created the schedule target, but forgot to assign it as the primary basleine. in which case, the target bars you see at the bottom are just the current schedule bars showing up as target bars.
2. you might have forgotten to check cell to display the primary baseline bars. You can do that by clicking on the bar options, and check the box against the primary baseline to be displayed.
Hope this helps.
raj
Hello James,
Unless you UPDATE TARGET , Tools>Project Uilities> Target and then update , selecting the required updates , it should not update the target and the taret bars should not move.
If you want you can send me the schedule to [email protected] and i will check it for you.
regards
pranab