Darren Kosa 👤 Member for 18 years 3 months

Hi Stuart,



I don’t use 2k7, but I’ve experienced similar problems in 2k3.



Most of them have been down to work / units driving the durations or split tasks affecting the start times of successors.



Try changing the date format to include hh/mm and then looking at the Start / Finish dates to see if anything stands out.



My default Start / Finish times are 08:00 and 17:00 so if I now see a Start or Finish that doesn’t fit in with that (excluding half days), then I’m pretty sure something is amiss.



Regards,



Darren