Total Slack
Forum Sponsor
Top Posters
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Thanks Darren,
I will investigate
Hi Stuart,
I don’t use 2k7, but I’ve experienced similar problems in 2k3.
Most of them have been down to work / units driving the durations or split tasks affecting the start times of successors.
Try changing the date format to include hh/mm and then looking at the Start / Finish dates to see if anything stands out.
My default Start / Finish times are 08:00 and 17:00 so if I now see a Start or Finish that doesn’t fit in with that (excluding half days), then I’m pretty sure something is amiss.
Regards,
Darren