I don’t use 2k7, but I’ve experienced similar problems in 2k3.
Most of them have been down to work / units driving the durations or split tasks affecting the start times of successors.
Try changing the date format to include hh/mm and then looking at the Start / Finish dates to see if anything stands out.
My default Start / Finish times are 08:00 and 17:00 so if I now see a Start or Finish that doesn’t fit in with that (excluding half days), then I’m pretty sure something is amiss.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks Darren,
I will investigate
Hi Stuart,
I don’t use 2k7, but I’ve experienced similar problems in 2k3.
Most of them have been down to work / units driving the durations or split tasks affecting the start times of successors.
Try changing the date format to include hh/mm and then looking at the Start / Finish dates to see if anything stands out.
My default Start / Finish times are 08:00 and 17:00 so if I now see a Start or Finish that doesn’t fit in with that (excluding half days), then I’m pretty sure something is amiss.
Regards,
Darren