if delay event is on first day of project start date then no updates available since project has just commenced .In this TIA looks like impacted as planned method is it correct?
If u show only one bar, then it may not solve the pupose.
This activity is linked with may be 100+ other activties. So, to demonstrate the impact you need to split this activity into different set of drawing activities and so, the impact of this on succeeding activities and on the project completion. If the start and end date of hammock activities remain same, and u insert few new activities, will give u a clear picture of the entire series of delay events.
While preparing a claim program, make sure that even ur site team will understand it and shud not remain a piece of paper from planner.
Right from day 1 indicative design been issued and contractors are working on it after 6 months consultant revealed that whole design got changed and they gave set of drawings {construction} .Asked contractor to proceed from the start of it again.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I mean to say introduction of delay event fragnet on planned program which looks similar to impacted as planned method ?
hi to all
if delay event is on first day of project start date then no updates available since project has just commenced .In this TIA looks like impacted as planned method is it correct?
Shahul,
If u show only one bar, then it may not solve the pupose.
This activity is linked with may be 100+ other activties. So, to demonstrate the impact you need to split this activity into different set of drawing activities and so, the impact of this on succeeding activities and on the project completion. If the start and end date of hammock activities remain same, and u insert few new activities, will give u a clear picture of the entire series of delay events.
While preparing a claim program, make sure that even ur site team will understand it and shud not remain a piece of paper from planner.
Cheers,
Hi Shahul
Put in a big red activity bar called Late Issue of Drawings.
Make it start from the day 1 and link it FS to the 1st activity that needs the drawings.
Make the end date Monday 16th November and re schedule.
Every week make the bar 1 week longer until you get the drawings.
Best regards
Mike Testro
Mike
Right from day 1 indicative design been issued and contractors are working on it after 6 months consultant revealed that whole design got changed and they gave set of drawings {construction} .Asked contractor to proceed from the start of it again.
Please advise how to proceed in TIA
Many thanks Mike .
Hi Shahul
How much actual work had been done following the wrong design?
If none then the TIA will be a bar between date of issue of wrong drawings to date of re-issue drawings with the same FS links in place.
This will demonstrate the likely completion of the project and the EoT.
If some work had been constructed then it may have to be replaced so demolition / break out work may need to be added.
This would be concurrent with the new design development / workshop drawings lead in for new construction.
The contractor will be entitled to be paid for all abortive design and construction work.
Best regards
Mike Testro
Thanks to all
On submission of delay event 1 TIA to consultant could we link event 1 with upcoming delay event 2 [ which is under preparation stage]