Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Wed, 2008-07-02 00:35 Permalink RE: P6 Activity codes No this cannot be done in P6, you have to manually create the project activity code and them transfer from global to project. Log in or register to post comments
Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Wed, 2008-07-02 00:35 Permalink RE: P6 Activity codes No this cannot be done in P6, you have to manually create the project activity code and them transfer from global to project.
Member for
20 years 6 monthsRE: P6 Activity codes
No this cannot be done in P6, you have to manually create the project activity code and them transfer from global to project.