P3 and P5/P6 are different programs, not just two different versions of the same one. So, many algorithms and procedures are different.
The way to produce and then save a report for export to EXCEL is rather easy. The produced format is csv and you can set a parameter that Excel automatically opens after the data was produced - the report ran. We produce most of our s-curves this way - just run the report. I dont miss the P3 ability.
Thanks for your reply, you are right but i guess in P5 we can not export "Resource Usage Spread sheet" in excel format. Where as in P3 we can get such outputs in formats like csv or wk1.There it used to help me in production of S-Curves with lot of flexibility.
Youll create a report with "Time Distributed Data" marked from the group Resource Assignments (or a similiar name). Then youll be guided by the wizzard. As output format youll select text/ASCII-file.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
can u do the favour the same to me,...
with regards,
Mr. Ameen N Pasha,
[email protected]
I am really thankful to both of you.
I am able to do it now.
Thank you once again
Mubashir
I try to give you a step by step guide. HTH
1. Open Your project
2. Then Click assignment
3. Change Timescale @ the spreadsheet to month or week
4. Highlight the activity
5. Click Ctrl C
6. Open Excel
7. Click Ctrl V
That should work
ALex
Mubashir
reporting in P5 is very easy. Try it.
Print resource usage profile:
View "Activities" --> "resource usage profile" --> File --> "Print Preview" --> "Page Set-up (The Icon upper left corner) --> walk through the detail tabs --> "Options" mark "Resource Usage Profile"
Regards
Dieter
i still unable to do it, one more query sir: how to print resource usage profile??
Mubashir
P3 and P5/P6 are different programs, not just two different versions of the same one. So, many algorithms and procedures are different.
The way to produce and then save a report for export to EXCEL is rather easy. The produced format is csv and you can set a parameter that Excel automatically opens after the data was produced - the report ran. We produce most of our s-curves this way - just run the report. I dont miss the P3 ability.
Just try it.
Regards
Dieter
Dieter Wambach
Thanks for your reply, you are right but i guess in P5 we can not export "Resource Usage Spread sheet" in excel format. Where as in P3 we can get such outputs in formats like csv or wk1.There it used to help me in production of S-Curves with lot of flexibility.
Please Comment
Mubashir
Youll create a report with "Time Distributed Data" marked from the group Resource Assignments (or a similiar name). Then youll be guided by the wizzard. As output format youll select text/ASCII-file.
Regards
Dieter