Bruce Mercer 👤 Member for 24 years 7 months

Why has not anyone recommended Fragnets for duplicating phases? Ive successfully stored and retrieved fragnets and have had troubles in the past retaining all my data with copy and paste.



Would 600 activities exceed capabilitites?



Has anyone experienced problems using fragnets?

A
Ali Hamouda 👤 Member for 24 years 5 months

Salam Mirza,



How are u doing nowdays?



in addetion to Mr.Paul Haris solution.

you can make the changes through Exel sheet.

copy the first phase and make all your changes through the functions of Excel(visual basic functions).



Then import your file to P3.



I hope this will help.



Regards



Ali

--------------------------------------------------

P
Paul Harris 👤 Member for 25 years 3 months

When you duplicate your new activities they will need a unique number.



You may use the copy and paste option and renumber the activities with this function.



Then use either a Global Change to reassign the Phase or the Copy Cell function.



The Global change will only work if you have an unique number (created when you paste) in the new activity code to filter on.



If you create one new Phase 2 activity and Organise by Phase then paste the new activities into the new phase by highlighting the new Phase 2 activity when you paste in all the activities will adopt this Phase Code.



Regards



Paul E Harris

www.eh.com.au

Featured Partner

Top Posters

Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts

Our Partners