What about all of the timephased data that you can export to EXCEL (and it draws the graph for you) with the "analyse timescaled data in EXCEL" button on the Analysis Toolbar?
See also the Analysis Toolbar, where you can export Cumulative Cost and Cumulative Work, as well as all of the Earned Value numbers to EXCEL, and it draws the graph for you.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
you can buy "S curves V2" VBA EXCEL application: http://www.cubixpm-scurves.com/en/
it allows to :
BR, Jean-Yves Moine.
What about all of the timephased data that you can export to EXCEL (and it draws the graph for you) with the "analyse timescaled data in EXCEL" button on the Analysis Toolbar?
hi! i also mean to ask the same thing as chin. Simply how t plot planned progress vs actual progress in terms of weighted %.
Is there also a way of adding a row in the gant chart to show the total cost of the project?
million thanks po!
maimai
Chin,
No, you will have to use MS Excel to generate S-Curve for MSP 2003 and before; or upgrade to MSP 2007 and use its Visual Reports
Alexandre
Been doing this all the time.
Just wonder is there any plug-in to let MSP to generate the curve just like Primavera Project Planner...
Read up on Earned Value in MSP Help.
See also the Analysis Toolbar, where you can export Cumulative Cost and Cumulative Work, as well as all of the Earned Value numbers to EXCEL, and it draws the graph for you.
Anything, says plan manhours VS earned manhours to-date, plan manhours VS actual spent to-date, plan cost to-date VS earned cost to-date etc.
plan vs actual of what?