RESOURCE DRIVING PROJECT

S
Suresh Sankarankutty PMP 👤 Member for 19 years 10 months

Dear Imaran,

Thank you very much. Yup that is the one i forgot.. "Instead of Task Dependent" we suppose to give " Resource Dependent"



Many many thanks.

Suresh

I
Imran Arshad 👤 Member for 18 years 7 months

Dear Suresh,

For resource driven project setting got to project window,click on Defaults tab then define percent complete as Units & activity type as resource dependent before adding activities in your project.Hope this will help.





Imran Arshad