Dear Imaran,
Thank you very much. Yup that is the one i forgot.. "Instead of Task Dependent" we suppose to give " Resource Dependent"
Many many thanks.
Suresh
Dear Suresh,
For resource driven project setting got to project window,click on Defaults tab then define percent complete as Units & activity type as resource dependent before adding activities in your project.Hope this will help.
Imran Arshad