2A1) Its up to you or your estimation team to decide. If your prices is still valid (e.g. no price inflation in your cost build up, no additional cost factors to consider, etc.), then you may use.
2A2) No, a subcontract cost is a direct cost for the Contractor (in most cases).
Sometimes, your RFQ (to Subcon) requires direct & indirect to be separate, so Contractor can also allocate them as direct & indirect in your price.
I suggest you consult to you estimation team to determine your pricing structure, since this may be different, depending on Client requirements.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Skan,
If no daywork rates were originally set up it doesnt stop you agreeing them later and amending the contract to suit.
As long as BOTH parties agree to it, any contract can be amended at a later date.
Skan,
2A1) Its up to you or your estimation team to decide. If your prices is still valid (e.g. no price inflation in your cost build up, no additional cost factors to consider, etc.), then you may use.
2A2) No, a subcontract cost is a direct cost for the Contractor (in most cases).
Sometimes, your RFQ (to Subcon) requires direct & indirect to be separate, so Contractor can also allocate them as direct & indirect in your price.
I suggest you consult to you estimation team to determine your pricing structure, since this may be different, depending on Client requirements.
Larry
Hi,
Thanks
Reference to A1:
Can we use the rate in the quotation & establish the qty so price up the variation?
Refernce to A2:
When you said "direct cost of Labour, Eqpt & matl", actual cost paid by the subcontractor to the labour & supplier?
Invoices to prove cost incured?
Then add indirect cost and OH & P?
Skan,
My answers are:
A1) Yes. You can not submit a daywork claim, if daywork is not established in you contract.
A2) Use conventional estimation practice. e.g, Direct Cost of Labor, Eqpt, Matls, + Indirect cost Supv & Mngt, Oh, P, etc.
A3) Yes, it can be different in every contract, it can come in Unit Price, LS, Daywork, Cost plus, etc.
Hope these help.
Larry