Hi Faried



My understanding of your question is that you are setting the LAD’s for the Employer to go into the Contract.



If so they must be a genuine ascertainment of the damage and or loss that will be suffered if the project is delivered late.



You must take into account:

Loss of income.

Rent on existing premises.

Finance Charges.

Standing Staff.

Consultancy Fees.

Insurances.

Currency Fluctuations.



If the LAD’s are set too high the Contractor will build in a contingency in his tender.



If there are no LAD’s then the damages are "At Large" and therefore limitless and few switched on Contractors will tender.



In most contracts the extension of time clause is set down to protect the Clients right to deduct LAD’s because he cannot penalise a contractor for his own defaults.



Best regards



Mike Testro

J
James Barnes 👤 Member for 18 years 10 months

erm, right. My understanding (from the last time I was threatened with LDs)



Liquidated damages are codified into the contract to make the claiming (and in somecases limitation) of damages easier to assess. Often they expressly replace Ascertained damages.



The most common formula I have seen is that LDs will be payable at a rate of $xxx (or yyy% of the contract sum) per day of delay to the contract completion upto a value not exceeding zzz% of the total contract value.



It will be codified in the contract. If it’s not there, then there are no LDs nominated and they can’t be claimed, the claimant would need to demonstrate ascertained damages (loss of rent etc) and probably go to court to get them.

Featured Partner

Top Posters

jeoffrey reyes
15 posts
Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts