My understanding of your question is that you are setting the LADs for the Employer to go into the Contract.
If so they must be a genuine ascertainment of the damage and or loss that will be suffered if the project is delivered late.
You must take into account:
Loss of income.
Rent on existing premises.
Finance Charges.
Standing Staff.
Consultancy Fees.
Insurances.
Currency Fluctuations.
If the LADs are set too high the Contractor will build in a contingency in his tender.
If there are no LADs then the damages are "At Large" and therefore limitless and few switched on Contractors will tender.
In most contracts the extension of time clause is set down to protect the Clients right to deduct LADs because he cannot penalise a contractor for his own defaults.
erm, right. My understanding (from the last time I was threatened with LDs)
Liquidated damages are codified into the contract to make the claiming (and in somecases limitation) of damages easier to assess. Often they expressly replace Ascertained damages.
The most common formula I have seen is that LDs will be payable at a rate of $xxx (or yyy% of the contract sum) per day of delay to the contract completion upto a value not exceeding zzz% of the total contract value.
It will be codified in the contract. If its not there, then there are no LDs nominated and they cant be claimed, the claimant would need to demonstrate ascertained damages (loss of rent etc) and probably go to court to get them.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Faried
My understanding of your question is that you are setting the LADs for the Employer to go into the Contract.
If so they must be a genuine ascertainment of the damage and or loss that will be suffered if the project is delivered late.
You must take into account:
Loss of income.
Rent on existing premises.
Finance Charges.
Standing Staff.
Consultancy Fees.
Insurances.
Currency Fluctuations.
If the LADs are set too high the Contractor will build in a contingency in his tender.
If there are no LADs then the damages are "At Large" and therefore limitless and few switched on Contractors will tender.
In most contracts the extension of time clause is set down to protect the Clients right to deduct LADs because he cannot penalise a contractor for his own defaults.
Best regards
Mike Testro
erm, right. My understanding (from the last time I was threatened with LDs)
Liquidated damages are codified into the contract to make the claiming (and in somecases limitation) of damages easier to assess. Often they expressly replace Ascertained damages.
The most common formula I have seen is that LDs will be payable at a rate of $xxx (or yyy% of the contract sum) per day of delay to the contract completion upto a value not exceeding zzz% of the total contract value.
It will be codified in the contract. If its not there, then there are no LDs nominated and they cant be claimed, the claimant would need to demonstrate ascertained damages (loss of rent etc) and probably go to court to get them.