How can I know the target progress in myPrimavera

N
niles luo 👤 Member for 20 years 6 months
K
K D 👤 Member for 18 years 8 months

Hi.

You also can see baseline bar in Gantt chart.

In activity tab -> choose customize view -> in Bar tab, buttom bar choose baseline.

Regards

I
Imran Arshad 👤 Member for 18 years 7 months

Dear Niles,

In My Primavera P6 follow these steps.

1.open ur project

2.click on work space

3.select customize

you will have list of columns from where u can define Basline data date & project baseline columns.





Imran