baseline update progress

A
A D 👤 Member for 19 years 1 month

Or otherwise, there must be an imposed finish date for the project. (MUST FINISH BY)



This will generate negative float. Check this too..

A
armando moriles 👤 Member for 23 years 5 months

Lorenzo,



Try to check if you have constraints applied on those activities that generate negative floats...



With regards to baseline updating, I agree with Anoon...



Regards,



Arman

A
Anoon Iimos 👤 Member for 19 years 9 months

you don’t have to make multiple copies of the baseline, i suggest you study what a Data Date is...

L
Lorenzo Tolentino 👤 Member for 19 years 1 month

thank you mr. anoon for your reply...however, how do i get the the planned progress of every activity for a certain period of time? what we usually do here is that i make a copy of the baseline schedule then i would run that copy, CTRL+F9, to get the planned progress...is there a better way? Tnx a lot...

A
Anoon Iimos 👤 Member for 19 years 9 months

i don’t understand why you’re doing it, in principle, you don’t have to update the Baseline, you update only the current schedule.



in updating baseline in order to get the planned progress, you don’t have to change anything, you update it perfectly as planned.

Forum Sponsor

Top Posters

Abkar Bannayan
25 posts
James Williams
75 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts