Numerous Amount of Positive Float

L
Leonard Mon 👤 Member for 18 years 9 months
L
Leonard Mon 👤 Member for 18 years 9 months

Hi James & Rav, thank you for your respective input.

I’ll do the checking now.



Highly appreciated.

best regards.



leonard

J
James Barnes 👤 Member for 18 years 10 months

Raviraj is right. Also, check that links to successor activities have not been deleted or that those activities have actually started without the survey having been finished.



It’s possible that the groundworks were logically linked in the baseline to start after the survey was 100% completed, for example, but that in the event they were able to start while the survey work was ongoing, either by reorganisation of the works or because the logical link was an oversimplification to start with. In this event it may be that there is no longer any successor activity contingent on the completion of the survey and the Float would extend to the end of the project itself. It should then be logically tied back into the activities that are still contingent on it

A
A D 👤 Member for 19 years 1 month

Just check teh end date of both the projects. Plz also check weather there any mandatory constrainst in the baseline program or not?



if end date has moved considerably, then TF is also going to get changed.



Cheers,



Ravi

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts