Tried the UDF route as well, but that doesnt have the desired effect either, due to not being able to set resource fields equal to the value in an activity field. Going to try excel next, but really wanted to avoid doing that as it adds another few steps to the process where errors can appear.
Primavera have suggested using the SDK, but I think that is one for when we have a bit more time.
Earned Value in P3e is computed at activity level from the Performance Percent Complete and the activity budget.
The best workaround would be to create a User Defined Fields to calculate a Resource Percent Complete and Earned Value from the Resource Budget (or do it in Excel)
but unfortunately that doesnt work properly with multiple Cost Accounts. Where an activity has multiple accounts, the summary bands contain multiple accounts as well.
Using the expense or resource views doesnt work either as EV is not an available field at that level, only at activity level.
Resources and Activities are the bottom level and this is where all the calculations start. WBS, OBS and CA are used for reporting levels. So its just the case of chnaging the reports from WBS to CA. If you go to Group you can select CA there.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Steve!
Tried the UDF route as well, but that doesnt have the desired effect either, due to not being able to set resource fields equal to the value in an activity field. Going to try excel next, but really wanted to avoid doing that as it adds another few steps to the process where errors can appear.
Primavera have suggested using the SDK, but I think that is one for when we have a bit more time.
thanks for the input though
Neil,
Earned Value in P3e is computed at activity level from the Performance Percent Complete and the activity budget.
The best workaround would be to create a User Defined Fields to calculate a Resource Percent Complete and Earned Value from the Resource Budget (or do it in Excel)
I would have thought an activity could only have 1 CA. If you are going to use P5 then you will have to break your activities down per CA.
CA is available against resources.
Thanks Mark,
but unfortunately that doesnt work properly with multiple Cost Accounts. Where an activity has multiple accounts, the summary bands contain multiple accounts as well.
Using the expense or resource views doesnt work either as EV is not an available field at that level, only at activity level.
Any other thoughts?
Hi Neil,
Resources and Activities are the bottom level and this is where all the calculations start. WBS, OBS and CA are used for reporting levels. So its just the case of chnaging the reports from WBS to CA. If you go to Group you can select CA there.
I hope this helps and puts you back on track.
Mark