P6 Interproject Relationship Imports

O
Oli Kallenborn 👤 Member for 18 years 6 months

That won’t help you maintain existing links in your existing project that you want to update.



That will merely keep the links in your new update.

W
Waseem Saber 👤 Member for 21 years 6 months

When you import you should untick the relationship between only copied activities, this should be able to bring all the relationships with other projects.



hope this helps.....



Waseem Saber