If you are not using the leveling function, you can use the native MSP field "priority".
But, If you want to preserve for the future the use of this function, I recommend to use a customisable field of MS Project (like number1), paste in this field the Pimavera Breakdown structure and sort with it !
If you are not using the leveling function, you can use the native MSP field "priority".
If you want to preserve for the future the use of this function, I recommend to use a customisable field of MS Project (like number1), paste in this field the Pimavera Breakdown structure ans sort with it !
That was my back-up plan, but I wanted to see if there was a way to group it the same way its grouped in the "drop-down menu," before trying that approach...for aesthetic reasons, but push come to shove, I could certainly try that. I just figured it if had assigned it in some priority in the "drop-down menu," there might be some way to also have it grouped in a similar fashion.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello,
If you are not using the leveling function, you can use the native MSP field "priority".
But, If you want to preserve for the future the use of this function, I recommend to use a customisable field of MS Project (like number1), paste in this field the Pimavera Breakdown structure and sort with it !
regards
Olivier Bécart
Hello,
If you are not using the leveling function, you can use the native MSP field "priority".
If you want to preserve for the future the use of this function, I recommend to use a customisable field of MS Project (like number1), paste in this field the Pimavera Breakdown structure ans sort with it !
regards
Olivier Bécart
Enter Priority
100,200,300,.................
sort by priority
Phil,
The only way to get is to show in the order that you want, is to apply an initial numeric coding. ie.
1. Project Management
2. Design.
3. Manufacture
4. Installation
5. Commissioning.
If you dont, then you are quite right in that it will order them alphabetically.
HTH.
James.
Also, I tried this, and it seems to be grouping alphabetically by "description" vs. the input code, so 1-SB had no impact but 1-Submittal did.
That was my back-up plan, but I wanted to see if there was a way to group it the same way its grouped in the "drop-down menu," before trying that approach...for aesthetic reasons, but push come to shove, I could certainly try that. I just figured it if had assigned it in some priority in the "drop-down menu," there might be some way to also have it grouped in a similar fashion.
Phil,
Why dont you say "Row 1=1-SB, Row 2=2-CN"?
This way, MSP will keep the order you want
Alexandre