new project problem "negative float" (p3e)

J
James Skelton 👤 Member for 21 years 1 month

If the old project had cross project (external links) then when you schedule in V5 it hold these links by using External early start or External late finish dates.



If you have cleared all your known constraints but still have the * in the date field then this might be your problem.



Run a filter for External early start or External late finish and clear any External dates then schedule your project.



Hope this helps

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi

This message - not all .. - is quite reliable: one minute of difference is a difference. For control, change your preferences to "show time".

Edit --> User preferences --> Dates

Then you’ll realize the difference.

For the other item, go into the view "Projects" --> Tab Dates and check "Must finish by". I assume you forgot one project.

Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts