Start float is the difference between the early and late start dates; Finish float is the difference between the early and late finish dates.



There’s one more option MOST CRITICAL FLOAT, it is the least of the start or finish floats.



:-)



Rav

K
Karim Mounir 👤 Member for 20 years 3 months

sometimes it is different when u assign mandatory constraints (whether start/finish).