MSP Task Word Wrap?

B
Bob Duncan 👤 Member for 22 years 3 months
B
Bob Duncan 👤 Member for 22 years 3 months

Thank you.

I tried that but it forces a gap between the GANNT Chart bars which makes them look strange. They need to stay together to show the visual flow from one task to the next.



Can I overcome this problem somehow?



Bob.



ps. I’m using Project 2002.

W
Will Russell 👤 Member for 23 years 2 months

Bob,



Depending on which version of MSP you’re using you should be able to adjust individually the height of the task line this way the text will automatically wrap.



Will